Dominanta-Energy signed a contract for a gas turbine delivery to the Verkh-Tarskoye field |
|
|
|
Dominanta-Energy signed a contract for a gas turbine delivery to the Verkh-Tarskoye field
The contract was signed with Novosibirskneftegaz following success in the tender on July 16, 2007. The scope of the contract includes engineering, construction, and the whole complex of instal-lation, commissioning and maintenance service of the gas turbine powerplant rated at 10.4 MW.
The powerplant will be set up on the base of two packaged Centrax CX 501-KB7 gas turbine power packages equipped with Rolls-Royce 501KB7 turbines each rated at 5.2 MW.
According to the contract Dominanta-Energy developed the project documentation and ob-tained its approval at the Central Acceptance Board.
At present Dominanta-Energy is delivering and assembling the following equipment: gas-preparation unit, heat-insulated booster compressors, 0.4 kW packaged main control board, switch board, 1600 kVA auxiliary transformer with the voltage capacity of 10.5/0.4 kW and flame tubes.
The simple-cycle powerplant will operate on casing head gas (the back-up fuel is diesel) at extremely low temperatures (down to 55°С below zero).
The project is going to be realised within 150 days. The commissioning is planned for the end of December 2007.
|