Privod delivered three turbogenerators for Eletskaya TETs combined cycle plant |
|
|
|
Privod delivered three turbogenerators for Eletskaya TETs combined cycle plant
They are two T-25-2U3 turbogenerators and T-12-2U3 turbogenerator.
The T-25-2U3 turbogenerators will operate with gas turbines manufactured by Salut. The capacity of the air-cooled T-25-2U3 turbogenerators is 25 MW, the turbine rotation speed is 3 000 rpm, the efficiency is 98%. To reduce noise emission the generators are located in the sound-proof enclosure.
The capacity of the T-12-2U3 turbogenerator is 12 MW, the turbine rotation speed is 3 000 rpm, the efficiency is 98%. It will operate with the steam turbine manufactured by Kaluga Turbine Works.
The operation in full production is planned for 2008.
|